Heatpipe roadworks slipping

The roadworks installing the heatpipe have slipped behind schedule. Vital Energi say this is because

  • installing the storm drain and sewer for the Winvic development on Latimer Road has taken longer than expected;
  • there has been unforeseen concrete and utilities congestion in All Saints Road and Lime Walk, and
  • County Council Access to Headington work at Roosevelt Drive/Old Road is currently over-running by two weeks.

Work in Latimer Road has been put back two weeks, and in Lime Walk one week. Work in Sandfield Road is still expected to start today (16 January). See the latest complete schedule here, or my map which shows the current works and what’s coming up next.